Florida Court Clarifies That a Defective Notice of Commencement Does Not AutomaticallyDefeat a Construction Lien

Oct 20
4 min read

Florida construction lien law is technical, deadline-driven, and unforgiving. A recent decision from Florida’s Fourth District Court of Appeal provides an important reminder, however, that not every defect in the lien process necessarily invalidates an otherwise enforceable construction lien. In James B. Martin, Inc. d/b/a Allpro Windows & Doors v. Moore, No. 4D2025-0517, 2026 WL 1884372 (Fla. 4th DCA July 1, 2026), the Fourth District addressed a dispute involving a window contractor, a defective Notice of Commencement, multiple property owners, and a construction lien foreclosure action.


What Went Wrong on the Job

The contractor entered into an agreement with one of the property owners to remove and replace ten windows. The owner was a life tenant. As part of the transaction, the contractor had the owner sign a blank Notice of Commencement, which the contractor later completed and notarized.


A payment dispute developed during installation, and the contractor ultimately recorded a construction lien against the property. After litigation began, the contractor learned that several additional individuals also held ownership interests in the property. One of those owners successfully obtained dismissal of the lien foreclosure claim against her because she had not been served with a Notice to Owner.


Following a bench trial, the trial court ruled against the contractor on the lien foreclosure claim. Among other things, the trial court concluded that the Notice of Commencement was defective because it failed to identify all the property owners. The trial court also concluded that the lien could not be enforced because work did not begin within 90 days after the Notice of Commencement was recorded.


What the Fourth DCA Said

The Fourth District agreed with the trial court on one important point: because the contractor was the party that completed the Notice of Commencement, the contractor bore the risk associated with errors contained in that document.

But that did not end the analysis.


The appellate court held that an insufficient Notice of Commencement does not automatically invalidate an otherwise properly recorded and served construction lien. The trial court therefore erred by treating the defective Notice of Commencement itself as a basis for refusing to enforce the lien.


The Fourth District also rejected the trial court’s conclusion that the contractor failed to timely commence work. The appellate court determined that taking measurements and ordering the windows within the applicable period was sufficient to satisfy the commencement requirement relied upon by the trial court. The lien foreclosure judgment was therefore reversed, and the case was remanded for further proceedings.


The Final Walkthrough

The decision is favorable to contractors in one important respect: a defective Notice of Commencement does not automatically kill an otherwise properly recorded and served construction lien. The Fourth District explained that the defect may instead affect when the lien attaches and, as a result, its priority against other interests in the property.


But contractors should not read James B. Martin as a free pass.

The contractor could not enforce its lien against one of the property owners because of a separate Notice to Owner problem. The case is a good example of how Florida’s Construction Lien Law can treat different mistakes very differently. One defect may cost priority. Another may cost lien rights altogether.


For contractors, think of lien rights as the stick and voluntary payment as the carrot. Use the carrot first. Talk through the problem, negotiate the bill, and give the owner an opportunity to pay. But do not give away the stick while those conversations are happening.


Once a statutory lien deadline passes, you may lose the leverage that was bringing the owner to the table in the first place.


Do Not Bet Your Lien Rights on This Case

Contractors, subcontractors, suppliers, and property owners should be particularly cautious about attempting to apply James B. Martin without legal advice.


James B. Martin, Inc. v. Moore provides useful authority for the proposition that an insufficient Notice of Commencement does not, standing alone, necessarily invalidate an otherwise properly recorded and served construction lien. But the case should be viewed as a specific appellate ruling, not a blanket exception to Florida’s Construction Lien Law.


If there is a problem with a Notice of Commencement, Notice to Owner, Claim of Lien, or lien deadline, do not assume the mistake is harmless and do not assume it is fatal. Different defects have different consequences under Florida’s Construction Lien Law. Get the issue reviewed before the deadline passes and the decision is made for you.


About the Author

Daniel Kersey is a Florida Board Certified Construction Law Attorney with Smith Campbell, PA, and the only Florida Board Certified Construction Law Attorney based in Lake County, Florida. His practice focuses on representing contractors, subcontractors, owners, developers, and other construction industry professionals in payment disputes, construction defect claims, lien and bond matters, contract disputes, and complex commercial litigation.

Daniel grew up around Central Florida agriculture and blue-collar trades, giving him a practical understanding of the businesses, jobsites, and people behind the disputes he handles. He regularly represents clients throughout Florida in both state and federal court. He can be reached at danielk@smithcampbellpa.com or 352-787-1241.